Grid connection
Grid architecture
The Dutch Energy Act, which entered into force on 1 January 2026, represents a landmark reform in the Dutch energy sector. Its aim to alleviate grid constraints by modernising the gas and electricity market and aligning Dutch law with the EU Clean Energy Package. The act distinguishes between the high voltage transmission system, operated by TenneT (“TSO”), and the local distribution systems, operated by several distribution system operators, such as Enexis (“DSO”). The Netherlands Authority for Consumers and Markets (“ACM”) is the independent national regulator.
As in other European jurisdictions, the Dutch system is founded on the principle of unbundling. In practice, this means that ownership and operation of transmission and distribution network assets are not available to third parties, such as data centre developers, on a standalone basis.
Grid connection, charging, congestion and queues
System operators are in principle required to offer a grid connection within a reasonable time – as ultimately determined by the ACM – and to realise it once accepted. Where insufficient capacity is available, an operator may refuse the request until constraints are resolved, though it remains obliged to expand the grid in the meantime – such refusals are increasingly giving rise to litigation, making careful review of the associated contracts ever more important. Customers can access the electricity grid through three main routes: firstly, transmission-level connections (typically at least 110 kV, for projects of around 100 MW or more); secondly, distribution-level connections (generally no more than 66 kV, for smaller-scale projects); or thirdly, alternative private network arrangements, such as a closed distribution system or a direct line. Data centre operators are increasingly turning to alternative arrangements to mitigate congestion and secure more flexible or faster access to capacity. System operators charge customers for the realisation of new connections, typically in stages under a milestone scheme. Once a connection is in place, customers are charged periodically for its maintenance, operation, and the transport of electricity. The associated tariffs are set by the ACM on the basis of each system operator’s total allowed revenues, reflecting pooled system costs that cannot be traced to an individual customer.
Grid congestion remains the most significant obstacle to data centre development in the Netherlands. As of 2025, queues are substantial: DSO applications number approximately 14,000, representing around 9 GW of demand, whilst more than 200 TSO requests account for around 38 GW. In some regions, new or upgraded connections have been temporarily suspended pending capacity expansions, with connection times in severely congested areas reaching up to ten years. Northern regions retain more available capacity, though this advantage is gradually eroding as electrification and industrial growth accelerate.
Allocation of scarce grid capacity
In congested areas, the default first come, first served (“FCFS”) allocation model no longer applies. In its place, the ACM has established a priority framework under which priority is given to congestion alleviators, safety-critical infrastructure, and essential public services – with priority among congestion alleviators determined by objective effectiveness. Within all other categories, and between parties without priority status, capacity is allocated on an FCFS basis. Data centres do not hold independent priority status but may qualify indirectly where capacity is used exclusively for a priority-sector party through a joint application.
The priority framework is still evolving and subject to ongoing litigation, with further clarification expected in 2027.
Flexibility mechanisms
Grid access in the Netherlands is actively managed to prevent overload, with system operators relying on flexibility mechanisms that require or incentivise large users – including data centres – to adjust consumption patterns. Three principal instruments are currently in use:
- Capacity steering contracts: Agreements under which users commit to reducing or increasing electricity consumption or supply depending on grid conditions, in exchange for financial compensation.
- Capacity limitation contracts: A specific form of capacity steering contract under which users commit only to reducing consumption or supply at specified times in exchange for financial compensation. These are the primary tool for securing ongoing grid access at congested nodes.
- Redispatch (via GOPACS): A short-term mechanism to adjust consumption or generation in near real time, operating through either voluntary participation or mandatory bids. Businesses with a connection of 60 MW or more are always required to offer flexible capacity.
Alternative transmission rights
In response to grid congestion, three types of non-firm transmission rights are available, each offering a different level of supply certainty:
- Fully variable transmission right: Provides grid access only when sufficient transport capacity is available, typically confirmed one day in advance. Supply is not guaranteed and operators must be capable of absorbing interruptions at short notice.
- Time-block transmission right: Grants access during predefined periods – such as off-peak or night-time hours – with no entitlement to capacity outside those windows. Offered by DSOs, this product suits operations that can be scheduled around fixed availability periods.
- Time-duration transmission right: Ensures grid access for a minimum proportion of time (typically around 85%), with advance notification of unavailable periods. Offered by the TSO, this is the most operationally predictable non-firm option and is generally the most relevant for operators requiring a baseline level of supply certainty.
These variants may be combined to construct a tailored solution aligned with a data centre's operational model and flexibility requirements. Single-owner data centres are generally better placed to participate in flexibility arrangements, as they can adjust aggregate consumption without contractual constraint, particularly where operators can shift or modulate workloads such as AI training to periods of greater grid availability. Co-location data centres face greater structural complexity: the presence of multiple tenants with distinct load profiles and service level commitments limits the operator's ability to curtail or shift consumption unilaterally.
Additional policy measures
As part of the National Action Programme on Grid Congestion, additional measures are being developed to enable more efficient use of existing grid infrastructure. These include a “use-it-or-lose-it” regime – allowing system operators to reduce contracted capacity where utilisation consistently falls below the contracted threshold – and group transport agreements, which allow multiple large customers to contract and allocate capacity collectively. For larger data centre campuses or operators running multiple co-located facilities, group transport agreements may offer a practical route to securing aggregate capacity unavailable to individual applicants.
Although no sector-specific interruptibility obligations currently apply to data centres, participation in flexibility arrangements is in practice increasingly a de facto prerequisite for securing and maintaining grid access, rather than a purely optional commercial choice.


