Grid connection
Securing grid access in a capacity-constrained market
One of the key constraints for data centre investors and developers in Portugal is securing grid access for large-scale consumption. The rapid growth in demand for grid connection capacity – driven in significant part by an influx of data centre investment projects – has placed considerable strain on the Portuguese public electricity supply network and has prompted a substantive regulatory response from the Portuguese Government.
In Portugal, there are two key network operators. Rede Elétrica Nacional, S.A. (“REN”) is the holder of the transmission system public service concession and serves as the Portuguese transmission system operator (“TSO”). E-Redes – Energia S.A. (“E-Redes”) is the holder of the distribution system (medium and high voltage) concession and serves as the Portuguese distribution system operator (“DSO”). E-Redes is also the holder of a significant majority of the low-voltage municipal distribution grids. On the regulatory side, the Energy Services Regulatory Authority (Entidade Reguladora dos Serviços Energéticos, “ERSE”) acts as the independent regulator of the energy sector.
The Portuguese national electricity system is built upon a clear model of unbundling network activities from competitive activities. These unbundling rules mean that the ownership and operation of transmission and distribution network assets are activities exclusively reserved for the concession-holders and are not open to third parties (including data centre developers) on a standalone basis. While the developer may be responsible for the construction of connection infrastructure connecting a consumer installation to the grid, the connection infrastructure may become the property of the relevant network operator and be integrated into the public grid. This means that a data centre developer with significant connection requirements could, in principle, co-finance grid reinforcement works, although the infrastructure itself could remain under the concession-holder's ownership and control.
The connection queue: reform, priority pathways, and capacity allocation
The standard framework on grid access and connection of consumption installations is mainly set out in the ERSE Commercial Relations Regulation, which governs the conditions for the connection of electricity consumption installations to the public grid. As a general rule, the connection process works on a “first-come, first-served" basis and is initiated by the developer submitting a request to the relevant network operator. Developers must provide the technical information requested by the operator to perform studies to evaluate whether it can grant the requested grid connection and if any grid reinforcement works are necessary. For connections above a certain capacity and voltage, construction conditions and timelines are agreed between the developer and the relevant network operator.
The Portuguese National Data Centre Plan (“PNCD”), approved by the Resolution of the Council of Ministers no. 2/2026, of 8 January (“RCM 2/2026”) and Resolution of the Council of Ministers no. 70/2026, of 13 April (“RCM 70/2026”), acknowledges that grid connection times in Portugal are typically between 2 to 5 years, a range that reflects not only the complexity of technical works but also the length of administrative and licensing procedures as well as grid works and availability.
Submarine cable connectivity is itself now the subject of EU-level resilience policy and dedicated funding under the Commission’s February 2026 Action Plan on Cable Security, a consideration relevant both to the durability of Sines’s locational advantage and to the structuring of any cable consortium participation.
The PNCD explicitly identifies constraints on access to the electricity grid as one of the key challenges affecting project execution in Portugal. The combination of a rapidly growing demand pipeline – driven by hyperscale and AI-related data centre projects – and the relatively long timelines for both grid reinforcement and administrative procedures has created a de facto queue for large consumption connections, particularly in areas of concentrated demand (for example the town of Sines, which is considered attractive to developers due to its port infrastructure, existing industrial grid connections, access to submarine cable landing stations and available land). Submarine cable connectivity is itself now the subject of EU-level resilience policy and dedicated funding under the Commission’s February 2026 Action Plan on Cable Security, a consideration relevant both to the durability of Sines’s locational advantage and to the structuring of any cable consortium participation.
The Government’s response to this congestion was through the implementation of an exceptional regime developed to allocate interconnection consumption capacity in areas of high demand (excluding low voltage connection requests), as set out in Decree-Law no. 80/2023, of 6 September (“DL 80/2023”). The procedure is intended to be open, transparent, equitable, and competitive, and encompasses multiple potential phases: (i) manifestation of interest and posting of a performance bond, combined with identification of unused capacity; (ii) evaluation of demand and network reinforcement; (iii) making unused capacity available and, where applicable, mandatory waiver and assignment of dormant capacity; and (iv) auction procedure if necessary.
In February 2026, the Portuguese Government launched a public consultation for the manifestation of interest in the allocation of consumption-connection capacity in a high demand area composed of the entirety of the continental territory for medium and high voltage connections with a capacity above 20 MVA.
Within the DL 80/2023 mechanism, priority treatment is available to priority projects. Priority project status is available to projects with project-of-national-interest (“PIN”) status in certain at-risk sectors (as defined under EU State aid guidance) or to projects funded under specific innovation agendas under Portugal's Recovery and Resilience Plan (“PRR”). While there is no explicit fast-track category reserved for data centres as such, the combination of PIN or PRR status and the priority project regime under DL 80/2023 provides the most direct pathway to preferential capacity allocation for strategically significant projects.
Grid connection capacity constraints in Portugal are not geographically uniform: they are most pronounced in areas of concentrated data centre demand. In response, extending the DL 80/2023 exceptional procedure to the entirety of the continental grid territory in 2026 represented a recognition that localised capacity for consumption constraints are becoming a nationwide challenge, rather than one confined to a single area.
Within the DL 80/2023 mechanism, the legislator seeks to satisfy the demand for connection capacity of electricity consumption installations required, through network reformulation or reinforcement, as well as redispatch measures and the introduction of flexibility measures. Measures currently being developed under the PNCD include the identification and enabling of pre-licensed zones with early-stage licensing and coordinated planning for grid connection, as well as a review and simplification of licensing procedures to ensure more efficient processing within maximum statutory decision deadlines, while maintaining applicable legal, technical, and environmental requirements.
Flexibility obligations, connection charging, and the use-it-or-lose-it discipline
Portugal does not currently impose sector-specific mandatory demand response or interruptibility obligations on large consumers such as data centres. There is, however, a form of capacity-specific "use-it-or-lose-it" discipline embedded in the exceptional connection capacity-allocation framework established by DL 80/2023, under which holders of allocated but unused grid connection capacity for consumption are notified and required either to present evidence of their need for the allocated capacity with a corresponding use timetable, or to voluntarily make the capacity available to meet demand from incoming applicants, with the warning that failure to do so may result in mandatory assignment.
Looking ahead, the PNCD’s Energy and Infrastructure axis includes an initiative, which aims to integrate energy efficiency criteria and demand flexibility mechanisms in planned grid connection infrastructure, promoting more efficient network use and greater resilience of the energy system. This initiative signals that the Government intends to formalise demand-side flexibility requirements as a structural element of future data centre grid connections, though the precise legal instruments and financial incentive mechanisms remain to be defined in implementing legislation.
The connection charging framework applicable to large electricity consumers – including data centres – is set out principally in ERSE Commercial Relations Regulation. As a general principle, the costs associated with a new connection are structured around the four main components: (i) costs of connection elements (the physical infrastructures linking the installation to the grid); (ii) a standardised network contribution, calculated by multiplying the ERSE-published unit value in €/kVA by the requested power, with the applicable unit value varying by voltage level and published periodically by ERSE; (iii) connection service charges, which cover items such as site visits, design documents, budgeting, and construction supervision; and (iv) third-party costs, which reflect costs incurred by the operator in connection with works carried out by third parties necessary to implement the connection. In relation to metering, large electricity consumers connected at medium, high or very high voltage are subject to mandatory remote metering under the applicable ERSE regulatory framework and network operator’s technical specifications, enabling both the network operator and suppliers to access such data for billing, settlement and network management purposes.


