Grid connection
Grid architecture and market structure
Access and connection to the electricity grid is probably the greatest roadblock to developing data centres in Spain today. As electricity consumers, obtaining demand-side grid access and connection rights, and maintaining their validity, is a critical factor for the success of data centre projects.
The Spanish electricity sector operates under a strict unbundling model. Transmission is carried out exclusively by Red Eléctrica de España (“REE”), the sole transmission system operator, under full ownership unbundling. Distribution is carried out by a limited number of distribution system operators subject to legal and functional unbundling.
As a result, data centres can only access physical electricity supply through: firstly, obtaining grid access and connection permits to the transmission grid (high voltage: 220 kV or higher) or distribution networks (medium or low voltage) (“A&C Permits”), which represents the primary route for connecting to the grid; or secondly, implementing behind-the-meter arrangements, although it should be noted that these are typically insufficient on their own for large-scale facilities. Spanish law does not currently allow for alternative grid access arrangements, such as microgrids, closed distribution networks, or energy communities.
In line with EU regulations, grid operation in Spain is a regulated activity, subject to exclusive or special rights and strict unbundling conditions. Therefore, no operators other than the authorised grid operators are permitted to provide grid access arrangements. Recent legislative reforms allow alternative grid access arrangements for certain specific cases (such as microgrids, closed distribution networks, or energy communities), but data centres do not qualify to participate in any of these alternatives. In other words, A&C Permits are their main mechanism to secure energy supply.
Limited grid capacity remains a major constraint on data centre development in Spain. According to recent surveys, it is estimated that the total grid connection requests for data centres reached approximately 8.7 GW, of which only around one in four MW had been awarded. To tackle this lack of grid capacity, the Spanish government approved targeted amendments to the transmission grid development plan in April 2024 and July 2025, and a new transmission grid plan is expected during 2026 (to be applicable until 2030). This plan will include mandatory developments of the grid, in order to attend new capacity needs (from both generation and demand sides). A&C Permits for data centres or other consumers can only be obtained at existing or planned grid nodes in positions designated for demand purposes. Recent regulatory amendments have sought to make node planning more flexible and to allow, in certain cases, grid extension or change of purpose of existing node positions to supply new demand facilities deemed strategic investment.
Connection queue: reform, maturity milestones, and competitive tenders
Grid capacity availability varies materially by location, making node selection a critical early step. Capacity maps published by grid operators are a key reference. The forthcoming 2025-2030 grid plan formally incorporates a 2,500 MW data centre target and is expected to identify the transmission reinforcements needed to accommodate projected demand. Although the 2025-2030 grid plan should have been approved by the end of 2024, its processing has been delayed due to, among other reasons, the emergence of new electricity-intensive demand facilities. However, said forthcoming grid plan would consider the demand needs of the years 2025 and 2026, while interim amendments of the previous grid plan were implemented as a bypass measure to attend to urgent grid capacity needs.
Spain’s grid access and connection framework for large consumers is comprehensively regulated through a single electronic process at national level, under standardised timelines and before the grid operator responsible for the relevant node. End-to-end timelines from A&C Permits request to energisation may range between 30 and 40 months under an optimistic scenario, assuming no tenders are called and depending on the scope of connection works required.
A&C Permits applications were historically processed on a “first come, first served” basis. To address speculation risk, competitive tender procedures can now be activated at overloaded nodes, though these procedures are yet to be thoroughly tested in practice. A&C Permits holders are now subject to binding project maturity milestones over a five-year window – including a grid works’ down-payment, execution of a grid reinforcement agreement and grid access contracts – with automatic permit lapse in case of non-timely compliance. In addition, with effect from June 2026, each sponsor is required to make monthly capacity reservation payments. During the first year, 100% of such capacity reservation payments will be credited against future tolls; thereafter, this proportion will reduce to 80%, with the remaining 20% being non-recoverable.
Sponsors must bear the full cost of private connection infrastructure and any required grid reinforcements. A structural constraint applies to campus or multi-tenant configurations: any connection infrastructure shared by more than one consumer is legally deemed part of the public distribution grid and must be transferred to the local DSO for no consideration, with a right of partial cost recovery if subsequently used by additional consumers.
A preferential access framework for “high priority” demand projects has been introduced; although whether data centres may benefit from this framework will depend on forthcoming implementing rules.
Flexibility, charging, and electricity supply
Data centres in Spain are not subject to any mandatory sector-specific demand response or interruptibility obligations by virtue of their nature or size. As a general rule, A&C Permits in Spain are granted on a firm basis, meaning the contracted capacity is guaranteed at all hours of the year. A flexible access regime is currently being developed by the Spanish Markets and Competition Regulatory Authority (Comisión Nacional de los Mercados y la Competencia, “CNMC”), which in July 2026 released a revised draft resolution for public consultation outlining the conditions under which demand facilities may hold flexible A&C Permits. Under this regime, the degree and nature of the flexibility afforded will vary depending on the type of permit granted, ranging from restrictions on the hours during which consumption is allowed to more active real-time interventions by the grid operator, such as remote disconnection or power reduction. However, this flexible regime allows one to obtain grid access connections where the available access capacity is scarce. Data centres are not obliged to opt for flexible A&C Permits, and in practice, are unlikely to do so given their operational requirement for uninterrupted power supply (unless otherwise mitigated with BESS facilities or other behind-the-meter alternatives). In respect of the electricity sector balance markets, although they are not obliged to participate in them, data centres may participate voluntarily in the interruptibility service or in demand response programmes managed by REE.
Power


